The Department of Transportation will be completing road work, including paving and milling, through Ditmas Park Wednesday and Thursday.
A list of locations the DOT plans to work on is available on its website. Here are some local areas that you can expect to see work.
On Wednesday, Aug. 8:
- Paving on East 23 St., from Beverley Rd to Ave. D.
- Paving on Vanderveer Pl., from Flatbush Ave. to East 23 St.
- Paving on East 25 St, from Clarendon Rd. to Foster Ave.
- Milling on southbound Ocean Pkwy Service Rd., from Ave. C to Ditmas Ave.
- Milling on northbound Ocean Pkwy Service Rd., from 18th Ave. to Caton Ave.
On Thursday, Aug. 9:
- Paving on East 25 St., from Clarendon Rd. to Foster Ave.
- Milling on southbound Ocean Pkwy Service Rd., from Ave. C to Ditmas Ave.
- Milling on northbound Ocean Pkwy Service Rd., from 18th Ave. to Caton Ave.
Be sure to check the schedule as it can often change throughout the week.